Integral Lifting and Construction Monitoring of an Irregular-Shaped Steel Connecting Corridor
-
摘要: 针对某多塔连体超高层建筑连桥结构重心偏位大、胎架支撑搭建环境复杂、整体提升高度大的特点,开展异形钢连桥高空整体提升专项分析。通过静力分析方法对连桥设计提升吊点进行确定,采用有限元模拟对连桥拼接阶段的特殊支撑胎架的承载力与稳定性进行校核,并对连桥同步、不同步两类提升过程结构受力情况进行分析。结果表明,在荷载组合作用下,连桥支撑胎架刚度、承载力与稳定性均满足相关规范要求。连桥提升过程中,同步提升阶段各杆件应力水平不高,且变形满足相关规范要求;而非同步提升纠偏阶段,采用双吊点纠偏方案可确保提升过程中连桥应力水平保持平稳。Abstract: In view of the large structural center-of-gravity deviation of a multi-tower connected high-rise building, the complex construction environment of the supporting trestles, and the ultra-high integral lifting, an integral lifting simulation analysis of an irregular-shaped steel connecting corridor was conducted. The lifting points of the steel connecting corridor were determined through structural static analysis, and the bearing capacity and stability of the supporting trestles were verified by finite element simulation. In addition, the structural behavior of the corridor during lifting was analyzed under two different conditions. The results showed that the stiffness, bearing capacity, and stability of the supporting trestles satisfied the specification requirements under the considered load combinations. During the synchronized lifting stage, the stress levels of the structural members remained relatively low, and the deformation complied with the specification limits. Furthermore, a double lifting point deflection correction method was shown to maintain stable stress levels in the connecting corridor during the unsynchronized lifting stage.
-
Key words:
- connected structure /
- steel connecting corridor /
- integral lifting /
- FEM /
- construction monitoring
-
[1] 刘中华,李建洪,苏英强,等. 现代空间钢结构施工方法综述[J]. 空间结构,2016,22(3):70-76. [2] Zheng J,Hao J P,Zhong W H. The mechanics analysis and research of multi-suspension-centers integral lifting technology for long-span steel roof[J]. Applied Mechanics and Materials,2012,170-173:3194-3198. [3] 沈蒲生. 多塔与连体高层结构设计与施工[M]. 北京:机械工业出版社,2009. [4] Ruan R L,Lai M H,Jiang C,et al. Integral lifting of steel structure corridor between two super high-rise buildings under wind load[J]. Buildings,2023,13(10):2441. [5] Xu C,Xu L,Zhou J. Integral lifting of a three-span continuous beam bridge[J]. Journal of Performance of Constructed Facilities,2014,29(4):04014117. [6] 魏巍,程春阳. 大跨连体钢结构整体提升技术[J]. 施工技术,2009,38(7):43-45. [7] 祁润田,许红胜. 异形空中钢连廊整体提升姿态调整策略研究[J]. 建筑结构,2019,49(增刊1):524-526. [8] 肖德高,刘艺芳. 高空悬臂钢连廊提升后微顶推施工技术[J]. 施工技术(中英文),2023,52(23):114-117. [9] 何超振,黎光军,佘勇,等. 高空大跨度悬挑钢连廊分段提升施工技术[J]. 建筑结构,2023,53(增刊2):1899-1904. [10] 司涛杰,夏天,卢伟超,等. 基于BIM的大跨度钢结构连廊施工方案仿真与实施[J]. 钢结构(中英文),2025,40(6):1-9. [11] Zhao Z W,Zhu H,Liu H B,et al. Thermal and integral lifting analysis of a lattice shell lighting roof based on genetic algorithm and probabilistic design[J]. Journal of Constructional Steel Research,2015,112:208-220. [12] 郭彦林,崔晓强. 大跨度复杂钢结构施工过程中的若干技术问题及探讨[J]. 工业建筑,2004,34(12):1-5. [13] 熊羽豪,肖从真,储德文,等. 泰康金融中心项目复杂连体结构设计关键问题研究[J]. 建筑结构学报,2024,45(6):39-49. [14] 张速. 有关结构空间桁架重心确定问题的探讨[J]. 安徽建筑,1998(增刊1):47-48. [15] 中华人民共和国住房和城乡建设部. 重型结构和设备整体提升技术规范:GB 51162—2016[S]. 北京:中国计划出版社,2016. [16] 中华人民共和国住房和城乡建设部. 钢结构设计标准:GB 50017—2017[S]. 北京:中国建筑工业出版社,2018. -
点击查看大图
计量
- 文章访问数: 4
- HTML全文浏览量: 0
- PDF下载量: 0
- 被引次数: 0



登录
注册
下载: