Shanjiang He, Weimin Xu, Chunchun Yu, Bin Liu. Research and Analysis Simulation on the Installation Plans of an Irregular Steel Structure[J]. STEEL CONSTRUCTION(Chinese & English), 2023, 38(11): 20-27. doi: 10.13206/j.gjgs23052301
Citation: Shanjiang He, Weimin Xu, Chunchun Yu, Bin Liu. Research and Analysis Simulation on the Installation Plans of an Irregular Steel Structure[J]. STEEL CONSTRUCTION(Chinese & English), 2023, 38(11): 20-27. doi: 10.13206/j.gjgs23052301

Research and Analysis Simulation on the Installation Plans of an Irregular Steel Structure

doi: 10.13206/j.gjgs23052301
  • Received Date: 2023-05-23
    Available Online: 2023-11-27
  • Publish Date: 2023-11-25
  • The irregular steel structures or steel-concrete composite structures of super high-rise buildings are not only subjected to very complex forces during the structural use stage, but also have particularly complex deformation and stress during the construction process. This project is a steel frame-core tube structure of special architectural form, with many oblique truss structures, whose top is strongly connected with the giant truss or core tube on the opposite side through horizontal members to be a "Mega-structure". There are significant differences in the stress forms of the main components of the steel truss before and after the overall structure synthesis. Therefore, it is considered that the vertical components and corresponding floors should be constructed layer by layer in the conventional sequence, while the diagonal steel truss should be assembled in place first, and the temporary support should be removed after the overall structure is formed, with the gravity load being applied at the same time. Besides, as the vertical stiffness of the core tube and truss varies greatly, the vertical deformation difference between them causes a large internal force on the member connected with the core tube. Because of this, in order to reduce the effect of vertical deformation difference, "release" is adopted in the design, which means the components next to the core tube adopt a method of subsequent fixation and installation to reduce the adverse impact of vertical deformation difference. In order to reduce the initial deformation and internal force of the structure in the process of construction, as well as achieve the above "release" requirements, two construction assembly plans, precise simulation and simplified simulation, were designed and formulated with considering the force requirement and the feasibility and economy of construction, and finite element program SAP2000 was used for calculation and comparison. The precise simulation plan refers to strictly following the construction sequence, fully considering the deformation and stress during the component assembly process, and accumulating them into the final internal force calculation and deformation control. Simplified simulation refers to forming most components in a computation model at once, with a focus on the impact of post installation and post consolidation of some components on the overall structure and related components. The main difference between the two schemes is that Scheme A considers that the newly assembled steel truss will be in a cantilever state for a period of time before the construction is completed, while Scheme B does not consider the impact of this part.
    Taking a typical steel truss as an example, this article specifically analyzes and compares the calculation results of the internal forces of the members and node displacements of the two schemes. Due to particularity of the construction plan for this project, the calculation model and parameters are specially processed to achieve accurate simulation of some steps in the construction plan.
    The results show that there is no significant difference in the internal force and deformation of the final state between the two simulation schemes, and the deformation modality and internal force distribution are similar. The variance of internal force in the final state of most components is less than 3%. According to the analysis results, the simplified simulation is selected to improve the analysis efficiency on the premise of ensuring the accuracy of calculation.
  • loading
  • [1]
    罗永峰,王春江,胨晓明.建筑钢结构施工力学原理[M].北京:中国建筑工业出版社,2009.
    [2]
    王化杰,范峰,支旭东,等.超高层结构施工竖向变形规律及预变形控制研究[J].工程力学,2013,30(2):298-312.
    [3]
    郭彦林,刘学武.大型复杂钢结构施工力学问题及分析方法[J].工业建筑,2007,37(9):1-8.
    [4]
    崔晓强,郭彦林,叶可明.大跨度钢结构施工过程的结构分析方法研究[J].工程力学,2006,23(5):83-87.
    [5]
    杨璐,尚帆,王宪璋,等.人民日报社综合楼钢结构安装施工模拟与变形控制[J].北京工业大学学报,2014,40(9):1361-1370.
    [6]
    周金良,李红现,梁建军,等.大型机场航站楼北连接体钢结构屋盖提升施工模拟分析[J].施工技术(中英文),2023,52(8):16-22.
    [7]
    宋博翰.混凝土收缩徐变对超高层结构竖向位移的影响研究[J].中国水运(下半月),2023,23(5):136-137.
    [8]
    苑会杰,马锦姝,王泽强,等.超高层结构竖向变形与伸臂桁架安装控制方法研究[J].建筑结构,2018,48(23):66-71.
    [9]
    戴苗,李治,涂建,等.带伸臂桁架的超高层混合结构施工模拟分析[J].建筑结构,2021,51(增刊2):1759-1764.
    [10]
    中华人民共和国住房和城乡建设部.建筑结构荷载规范:GB 50009-2012 [S].北京:中国建筑工业出版社,2008.
    [11]
    中华人民共和国住房和城乡建设部.高层民用建筑钢结构技术规程:JGJ 99-2015 [S].北京:中国建筑工业出版社,2015.
  • 加载中

Catalog

    通讯作者: 陈斌, bchen63@163.com
    • 1. 

      沈阳化工大学材料科学与工程学院 沈阳 110142

    1. 本站搜索
    2. 百度学术搜索
    3. 万方数据库搜索
    4. CNKI搜索

    Article Metrics

    Article views (341) PDF downloads(23) Cited by()
    Proportional views
    Related

    /

    DownLoad:  Full-Size Img  PowerPoint
    Return
    Return