Volume 40 Issue 8
Aug.  2025
Turn off MathJax
Article Contents
Gao Hui, Wang Gang, Zhou Xiaju, Tang Wei, Zhao Caiqi. Analysis and Monitoring of the Construction Process: Synchronous Cumulative Sliding Lifting of a High⁃Altitude Double⁃Layer Steel Truss Corridor[J]. STEEL CONSTRUCTION(Chinese & English), 2025, 40(8): 51-62. doi: 10.13206/j.gjgS25051201
Citation: Gao Hui, Wang Gang, Zhou Xiaju, Tang Wei, Zhao Caiqi. Analysis and Monitoring of the Construction Process: Synchronous Cumulative Sliding Lifting of a High⁃Altitude Double⁃Layer Steel Truss Corridor[J]. STEEL CONSTRUCTION(Chinese & English), 2025, 40(8): 51-62. doi: 10.13206/j.gjgS25051201

Analysis and Monitoring of the Construction Process: Synchronous Cumulative Sliding Lifting of a High⁃Altitude Double⁃Layer Steel Truss Corridor

doi: 10.13206/j.gjgS25051201
  • Received Date: 2025-05-12
    Available Online: 2025-10-27
  • Publish Date: 2025-08-22
  • A certain hotel project has set up a high-altitude double-layer steel truss corridor between two towers, with a span of 69.5 m and a total mass of 3485 t, using Q420GJC box-section components. Due to site limitations (only a 20 m × 70 m working surface) and cost control for machinery, a steel column support platform assembly sliding technology was selected. The overall lifting was achieved after accumulating three sliding cycles. By analyzing the phased assembly sliding and overall lifting processes, and combined with construction process monitoring, the structural safety was ensured. The truss structure was divided into four sliding units, namely Unit 1, Unit 2, Unit 3, and Unit 4, and they were installed using the "cumulative sliding installation" method. A slip analysis model was established based on the slip process. Firstly, only the self-weight load was applied to extract the reaction force at each fulcrum, which was converted into frictional force and applied to the slip analysis model. The calculation results showed that the maximum vertical displacement of the truss during the sliding process was -4.8 mm, and the maximum stress ratio was 0.112. The strength and stiffness of the structure during the sliding process met the requirements. Based on the analysis results of the sliding process, the fulcrum reaction force and friction force were extracted and applied to the sliding beam analysis model. The results showed that the maximum vertical displacement occurred at the edge sliding beam, with a maximum vertical displacement of -7.3 mm. The maximum stress ratio of the supporting component was 0.789, and both the displacement and stress ratio of the sliding beam were below the limit. According to the analysis results, monitoring points were set up at locations with high stress and displacement during the sliding process of the truss and sliding beam. The monitoring results showed that the stress and displacement at each measuring point during the sliding process were lower than the calculated results.After sliding to the design position below, the synchronous lifting construction phase was carried out. This involved utilizing the surrounding tower structural columns to set up lifting brackets and install lifting equipment to serve as lifting points. Lower lifting points were established on the upper chord of the truss structure, which were then reinforced with stiffening members. After the suspension points were fine-tuned to level the structure, the formal lifting process commenced. The process was paused every 5 meters to adjust the structural alignment until it reached the design position.The lifting process analysis model and the lifting bracket analysis model were established based on the lifting process and structural layout. The results indicated that as long as the asynchronous lifting value was guaranteed not to exceed 25 mm during the lifting process, the impact of asynchronous effects on structural safety could be neglected. The maximum displacement of the structure occurred at the mid-span location, with a maximum vertical displacement of 20.8 mm. The lifting truss exhibited a maximum stress ratio of 0.269, while the stiffening members showed a maximum stress ratio of 0.723. The maximum vertical displacement and maximum stress ratio of the lifting brackets were -7.2 mm and 0.783, respectively. Both the strength and stiffness of the lifted structure and brackets met the specified requirements. According to the analysis results, monitoring points were set up at locations experiencing high stress and displacement on the truss and lifting brackets. The monitoring results showed that the stress and displacement at each measuring point during the lifting process were lower than the calculated values.
  • loading
  • [1]
    中华人民共和国住房和城乡建设部. 钢结构设计标准:GB 50017—2017[S]. 北京:中国建筑工业出版社,2018.
    [2]
    中华人民共和国住房和城乡建设部. 建筑结构荷载规范:GB 50009—2012[S]. 北京:中国建筑工业出版社,2012.
    [3]
    王建国,张伟. 大跨度钢结构液压同步滑移施工技术[J]. 施工技术,2020,49(8):45- 49.
    [4]
    王光武,郑雪松,袁贵福,等. 大型体育馆屋盖钢结构累积滑移+散拼施工技术[J]. 施工技术(中英文),2021,50(6):38- 42.
    [5]
    姬建华,刘新乐,赵庆国,等. 高铁站房异形钢桁架屋盖曲面累积滑移施工关键技术[J]. 施工技术(中英文),2021,50(20):49- 52,74.
    [6]
    中华人民共和国住房和城乡建设部. 重型结构和设备整体提升技术规范:GB 51162—2016[S]. 北京:中国建筑工业出版社,2016.
    [7]
    王钢,陈桥生,闫西峰,等. 超长不规则回字形空间桁架提升点优化布置与非同步提升控制研究[J]. 施工技术(中英文),2025,54(3):63- 54.
    [8]
    贾尚瑞,邢遵胜,豆德胜,等. 万达茂滑雪乐园西区钢结构提升施工关键技术[J]. 施工技术,2015,44(8):9- 12.
    [9]
    王洽亲,张其林,罗晓群,等. 重庆江北机场T3B航站楼大厅屋盖钢结构提升施工技术[J]. 施工技术(中英文),2024,53(2):1- 6.
    [10]
    余少乐,雷克,孙晓阳,等. 南京牛首山树状钢结构提升系统设计[J]. 钢结构(中英文),2019,34(11):100- 103.
  • 加载中

Catalog

    通讯作者: 陈斌, bchen63@163.com
    • 1. 

      沈阳化工大学材料科学与工程学院 沈阳 110142

    1. 本站搜索
    2. 百度学术搜索
    3. 万方数据库搜索
    4. CNKI搜索

    Article Metrics

    Article views (59) PDF downloads(11) Cited by()
    Proportional views
    Related

    /

    DownLoad:  Full-Size Img  PowerPoint
    Return
    Return