Ning Zhang, Lijun Li. Design and Research of Main Weld of Track Beam of Suspension Monorail[J]. STEEL CONSTRUCTION(Chinese & English), 2021, 36(6): 36-43. doi: 10.13206/j.gjgS20071001
Citation: Ning Zhang, Lijun Li. Design and Research of Main Weld of Track Beam of Suspension Monorail[J]. STEEL CONSTRUCTION(Chinese & English), 2021, 36(6): 36-43. doi: 10.13206/j.gjgS20071001

Design and Research of Main Weld of Track Beam of Suspension Monorail

doi: 10.13206/j.gjgS20071001
  • Received Date: 2020-07-10
    Available Online: 2021-09-16
  • The track beam of suspension monorail is a combination of beam and rail structured by a thin-walled box with an opening at lower location and deck layout lower than the load-bearing structure. The main weld of flange and web on track beam is critical weld with force transferred by structure. The main weld has a complex load-carrying status which is difficult to design and check by conventional design method. Therefore, on the basis of the existing international design of track beam of suspension monorail and with reference to the Zhong Tang New Resource Sky Train Test Line Project participated by our company, the method combining finite element and theoretical calculation was used to analyze and calculated the load-carrying status of the main weld of track beam of suspension monorail. The transferring force rule of main weld seam of top/bottom flange of the track beam, main weld seam in region 1 and main weld seam along the beam length direction were studied. By the transferring force calculation of weld seam, track beam the main weld seam design of was carried out, in accordance with the Code for Design on Steel Structure of Railway Bridge (TB 10091-2017), and the weld seam strength and fatigue have been checkup. By this design method, the main weld of track beam of suspension monorail could be analyzed quantitatively, so as to avoid the main weld from being designed with overlarge size or exceed the actual need to reduce investment cost. The relevant conclusions were as follows:
    1) A stress analysis for the main weld (connecting web and top/bottom flange) of the track beam of suspension monorail was comlished. The top/bottom flange and web were connected by main welds and stiffeners. The bottom flange, as the vehicle travelling surface, was subjected to the local load effect given by the wheel, thus its weld seam bore the most stress.
    2) The main weld seam connecting the top/bottom flange and web were subjected to the shear effect, with the basically same shear force magnitude and the opposite shear force direction on the same section, with the calculation results concurring with the simply supported beam main weld seam capability of shear force; main weld seam of the bottom flange in the middle of the two stiffeners showed a definitely better capability of bearing vertical stress compared to the main weld seam of the top flange; bottom flange weld seam at stiffeners presented a slightly better capability of bearing vertical stress compared with top flange weld seam at stiffeners, with both of which better than the bottom flange weld in the middle of the two stiffeners in terms of bearing vertical stress; Mx moment of force of bottom flange weld seam in the middle of two stiffeners was significantly larger than any other positions.
    3) The vertical force in the stiffener was much larger than any other positions; the closer the longitudinal Fx to the stiffener, the quickly the Fx at stiffeners reduced under the effect of the stiffener; Mx distributed as a "V" shape, in which the least moment of force at stiffener, and it gradually increased to both sides. My distributed as a "M" shape.
    4) The transferring force rule of Fx gradually growed from the middle of the span to the support position, Fx in Q 1 position close to hanging suspension frame position reduced because the hanging suspension frame bore the shear force exerted by the track beam. Fx in the middle of each stiffener gradually growed from the middle of the span to the support position. The vertical force Fz was mainly caused by vehicle wheel, with the basically same magnitude at each location. From the middle of the span to support location, Mx reduced at first and then increased, My increased gradually.
  • loading
  • [1]
    余浩伟,徐银光,李涛,等.悬挂式单轨交通在国内的适应性研究[J].铁道工程学报,2019(4):70-74.
    [2]
    孙镠阳.跨座式单轨与悬挂式单轨比较分析及应用展望[J].城市道桥与防洪,2018(5):307-310.
    [3]
    康兴东,徐崇,张国栋,等.日本悬挂式单轨系统的应用与发展[J].国外铁道车辆,2019(5):1-7.
    [4]
    胡步毛,潘妍,鲁昭,等. 我国首条悬挂式单轨试验线建设实践[J].都市快轨交通,2019,32(1):38-42.
    [5]
    王洪波, 龚象山. 悬挂式单轨交通轨道梁制作工艺研究[J].工程技术研究, 2018(14):15-16.
    [6]
    谢倩. 悬挂式单轨系统轨道梁结构优化设计研究[D]. 成都:西南交通大学,2016.
    [7]
    杨平,鲍玉龙,曾永平,等.悬挂式单轨交通系统桥梁结构的选型设计[J].铁道工程学报,2016(7): 30-35.
    [8]
    肖云霞. 基于ABAQUS的悬挂式单轨系统轨道梁结构优化设计研究[D]. 成都: 西南交通大学,2016.
  • 加载中

Catalog

    通讯作者: 陈斌, bchen63@163.com
    • 1. 

      沈阳化工大学材料科学与工程学院 沈阳 110142

    1. 本站搜索
    2. 百度学术搜索
    3. 万方数据库搜索
    4. CNKI搜索

    Article Metrics

    Article views (185) PDF downloads(24) Cited by()
    Proportional views
    Related

    /

    DownLoad:  Full-Size Img  PowerPoint
    Return
    Return