Research on Integral Lifting of Floating Truss Structure Based on Ring Hoop Reinforcement System
-
摘要: 湖南广播电视台节目生产基地及配套设施建设项目中漂浮办公室单体为多筒支承的大平面多层桁架结构,由于该结构体系采用常规搭设支撑原位安装方案所需措施量巨大且安装周期长,如采用整体提升方案,结构脱离核心筒后离散为多个桁架单体,施工难度大。针对以上难题,研发了一种环形箍加固工装体系和提升单元变形及合龙精度控制成套技术,将多个离散单体转换成具有足够抗侧和抗扭刚度的整体结构体系,实现提升作业和精确合龙,同时简述了整体提升结构体系受力特点并揭示其提升状态作用机理。
研究内容及结论包括:1)通过深入分析核心筒和悬挑桁架单体协同作用机理,设计环形箍加固工装代替原核心筒约束和传力作用,将脱离核心筒后的漂浮桁架结构零散单体紧密拉结,在整体提升状态下可提供足够强度和刚度,使多零散桁架单体加固后满足整体提升施工要求;2)利用有限元软件MIDAS-Gen研究环形箍加固工装体系在提升状态下的传力模式和受力特性,将其进一步优化为提升吊点和下方横梁组成的扁担梁形式受力体系。扁担梁两端悬挑桁架一定程度上受力自平衡,虽然结构体系精简,但是传力路径更加直接,竖杆传力和水平杆刚度控制作用得到充分发挥。根据有限元计算结果对比分析发现,相比于优化前环形箍加固工装,优化后提升结构体系桁架悬挑端部竖向变形减小约10%~12%,对整体结构变形控制更加有利,且提升点优化一半,提升同步性更易保证,措施量优化约30%;3)本工程漂浮办公室提升就位后共120个合龙口,其合龙精度是漂浮办公室南区施工质量控制的决定性因素。利用有限元软件MIDAS-Gen计算分析漂浮桁架结构在提升状态下的变形趋势和合龙口错缝规律,研究发现对提升单元悬挑端部关键点位在拼装阶段过程中的反向预调,可有效保证对接口合龙和结构整体成型精度;4)通过对漂浮桁架结构从拼装到完成合龙全过程的变形监测,发现监测点实测的相对变形与施工模拟的结果变化趋势基本一致,提升和卸载过程中未发现过大的结构变形,验证了所提出的环形箍加固工装体系和提升单元变形及合龙精度控制成套技术的可靠性。Abstract: The floating office project of Hunan Radio and Television Station is a large plane multi-layer truss structure supported by multiple tubes. At present, the conventional in-situ construction scheme for the structural system requires a huge amount of measures and a long installation cycle, if the overall lifting construction scheme is adopted, the structure separated from the core tube is separated into several truss units, it is difficult to construct. For the above problems, a ring hoop reinforcing tooling system and a complete set of lifting structure deformation and closing precision control technology were developed, the discrete truss units were converted into integral structural system with sufficient lateral and torsional stiffness, which was satisfied for lifting construction and precise closure, at the same time, the mechanical characteristic of the whole lifting structure system were described and the mechanism in the overall lifting state was revealed.
The research contents and conclusions include:1) Through in-depth analysis of core tube and cantilever truss monomer synergistic effect mechanism, the ring hoop reinforcing tooling system is designed to replace the restraint and force transmission of the original core tube, provides sufficient strength and stiffness in the overall lifting state, the multiple scattered truss monomer can meet the overall lifting construction requirements after reinforcement; 2) Finite element software MIDAS-Gen is used to study the force transfer mode and mechanical characteristics of the ring hoop reinforcement tool system in lifting state, it is further optimized as a mechanical system of carrying pole girder composed of lifting point and bottom beam. The cantilevered trusses at both ends of the carrying pole girder are self-balanced to some extent, although the structure system is simplified, the force transmission path is more direct, the functions of vertical rod force transmission and horizontal rod stiffness control are given full play. According to the comparison analysis of finite element calculation results, compared with the ring hoop reinforcement tooling before optimization, the vertical deformation of the cantilever ends of the lifting structural system is reduced by 10%~12% after optimization, it is more advantageous to control the deformation of the whole structure, and the lifting point is optimized by half, the synchronization of structural lifting is easier to ensure, the measure quantity is optimized by about 30%;3) After lifting the floating office in place, there are 120 seams, its closed precision is the decisive factor for the construction quality control of floating office in the south area. Finite element software MIDAS-Gen is used to calculate and analyze the deformation trend of floating truss structure in lifting state and the regularity of the staggered joints of the closure. It is found that reverse pre-adjustment of the key points of the cantilever end of the lifting unit in the assembly phase can effectively ensure the closing and the overall forming accuracy of the structure; 4) Through the deformation monitoring of floating truss structure from assembling to closing, it is found that the variation trend of the measured relative deformation is basically consistent with that of the result of construction simulation calculation, no excessive structural deformation occurred during lifting and unloading, the reliability of the ring hoop reinforcement system and the complete set of deformation of lifting unit and closing precision control technology are verified.-
Key words:
- steel structures /
- floating truss /
- integral lifting /
- reinforcement measure /
- simulation analysis
-
[1] 董石麟.中国空间结构的发展与展望[J].建筑结构学报, 2010, 31(6):38-51. [2] 沈祖炎, 温东辉, 李元齐.中国建筑钢结构技术发展现状及展望[J].建筑结构, 2009, 39(9):15-24, 14. [3] 肖建文, 余伟华.大跨度超重钢连廊整体提升施工技术[J].钢结构(中英文), 2019, 34(9):83-86, 42. [4] 郭彦林, 田广宇, 周绪红, 等.大型复杂钢结构施工力学及控制新技术的研究与工程应用[J].施工技术, 2011, 40(1):47-55. [5] 吴穷, 王乾坤, 任志刚, 等.大跨度钢结构施工过程仿真分析[J].工业建筑, 2018, 48(3):127-131. [6] 杜丹, 潘剑峰, 刘晓斌, 等.中建·光谷之星1 300 m"回"字形连廊群提升施工技术[J].钢结构(中英文), 2019, 34(9):87-90. [7] 李立彪, 王幸男, 付玉香.钢屋盖整体提升监测技术[J].建筑技术, 2019, 50(9):1081-1083. [8] 孙学根, 牛忠荣, 方继, 等.安徽霍邱体育馆钢结构屋盖累积滑移施工法与监测[J].工业建筑, 2017, 47(6):125-130.
点击查看大图
计量
- 文章访问数: 263
- HTML全文浏览量: 68
- PDF下载量: 9
- 被引次数: 0