Study on the Design of Main Girder of Wide Steel Box Girder Cable-Stayed Bridge with Single-Column Pylon
-
摘要: 随着铁路安全要求的越来越严格,上跨铁路的市政工程桥梁跨径正在逐渐增大。为解决跨越高速铁路及大型铁路编组站的建设难题,以一座大跨度独柱中央索转体斜拉桥为研究对象,针对主梁设计进行详细研究。跨铁路通道一般为稀缺通道资源,搭载交通功能需求多,桥面往往较宽,若采用混凝土截面,其横向应力很难有效控制,且施工质量很难保证。钢混组合梁工艺复杂且需向铁路局要天窗点,施工时间长,考虑跨越铁路尽量施工方便且对铁路影响降到最低,同时尽量降低转体重量,推荐钢箱梁作为跨铁路桥主梁结构形式。根据斜拉索布置形式及整、分幅钢箱梁类型,共对三种钢主梁横向布置进行比选。由于采用独柱形桥塔且塔高较低,钢箱梁两侧布置的斜拉索将会倾入行车道净空,同时分幅钢箱梁中央护栏区仍存在车辆或异物坠入桥下铁路的危险,推荐中央索面整幅钢箱梁结构形式。在确定斜拉桥主梁结构形式为整幅钢箱梁的基础上,进一步优化钢箱梁梁高。以斜拉桥结构受力状态和钢材用量为优化目标,初步选定三种钢箱梁梁高方案,其截面高度分别为3.0,3.3,3.5 m。从结构受力状态和工程经济性两个方面综合考虑,3.3 m梁高方案对于主梁、桥塔受力及工程材料的节约方面为最佳配置。
为研究宽幅钢箱梁受力性能,以独柱塔宽幅钢箱梁斜拉桥工程实例,开展宽幅钢箱梁设计研究。基于极限状态法,依托JTG D64—2015《公路钢结构桥梁设计规范》开展了钢箱梁静载计算和疲劳计算分析。静载分析包括加载模式、钢箱梁桥面板刚度条件等指标的确定,并基于ANSYS开展了标准钢箱梁和压重区钢箱梁的空间局部应力分析;疲劳验算通过选择合理的疲劳荷载模型和全面考虑疲劳荷载的不同加载位置。静载计算和疲劳验算结果表明:大桥钢箱梁的静载变形和应力满足JTG D64—2015要求,各构件和连接的疲劳应力幅均小于规范限值,并有适当的安全富余,疲劳性能良好。采用杆系、板壳混合有限元法建立混合有限元模型,对独柱宽幅钢箱梁斜拉桥控制性区域跨中节段、塔梁交汇区域与边跨辅助墩区域进行剪力滞效应分析,提炼参数指标,对设计起到了重要指导作用。独柱塔宽幅钢箱斜拉桥主梁具有良好的经济性和美观性,可为大跨度宽幅桥面结构提供借鉴和参考。Abstract: With the increasingly strict requirements of railway safety, the span of municipal engineering bridge over the railway is gradually increasing. In order to solve the construction problems of crossing high-speed railway and large-scale railway marshalling station, a long-span single column central cable-stayed bridge was taken as the research object, and the main beam design was studied in detail. The cross railway channel is generally a scarce channel resource, with many traffic functions and wide bridge deck. If the concrete section is used, its transverse stress is difficult to effectively control and the construction quality is difficult to guarantee. The process of steel-concrete composite beam is complex and needs to be pointed out to the Railway Administration for a long construction time. Considering that it is convenient to cross the railway and minimize the impact on the railway, and at the same time reduce the weight of swivel as far as possible, steel box girder was recommended as the main beam structure form of railway crossing bridge. According to the layout of stay cables and the types of integral and split steel box girder, three kinds of transverse arrangement of steel girder were compared and selected. Due to the low height of pylon and pylon of single column bridge, the stay cables arranged on both sides of steel box girder would incline into the traffic lane clearance. Meanwhile, there is still the risk of vehicles or foreign matters falling into the railway under the bridge in the separation of steel box girder central guardrail area. The whole steel box girder structure with central cable plane was recommended form. On the basis of determining that the main beam structure of cable-stayed bridge was the whole steel box girder, the height of steel box girder was further optimized. Taking the stress state of cable-stayed bridge structure and steel consumption as the optimization objectives, three kinds of steel box girder beam height schemes were preliminarily selected, with the section height of 3.0, 3.3, 3.5 m respectively.
Considering the stress state of the structure and the engineering economy, the 3.3 m beam height scheme was the best configuration for the stress of main beam and pylon and the saving of engineering materials. In order to study the mechanical performance of wide steel box girder, the design and research of wide steel box girder cable-stayed bridge with single column pylon was carried out. Based on the limit state method, the static load calculation and fatigue analysis of steel box girder were carried out. The static load analysis included the determination of loading mode, stiffness condition of steel box girder bridge deck and other indicators. Based on ANSYS, the spatial local stress analysis of standard steel box girder and steel box girder in ballast area was carried out. The fatigue calculation was carried out by selecting a reasonable fatigue load model and considering different loading positions of fatigue load comprehensively. The results of static load calculation and fatigue check showed that the static load deformation of steel box girder of bridge and the stress met the requirements of the code, the fatigue stress amplitude of each component and connection was less than the standard limit value, and there was appropriate safety margin, and the fatigue performance was good. In this paper, a hybrid finite element model was established by using the mixed finite element method of member system and plate shell. The shear lag effects of the mid span section, the intersection area of pylon and beam and the auxiliary pier area of side span in the control area of single column wide steel box girder cable-stayed bridge were analyzed, and the parameter indexes were extracted, which played an important guiding role in the design. The main girder of single column pylon wide steel box cable-stayed bridge has good economy and aesthetics, which could provide reference for long-span and wide bridge deck structure.-
Key words:
- single column pylon /
- wide width /
- cable-stayed bridge /
- shear lag /
- steel box girder
-
[1] 周继, 张晓江, 田芳. 城市快速通道跨越铁路大型编组站桥梁方案比选研究[J]. 铁道标准设计, 2016, 60(5):59-64. [2] 中华人民共和国住房和城乡建设部.城市桥梁设计规范:CJJ 11—2011[S]. 北京:中国建筑工业出版社, 2019. [3] 刘明虎, 孟凡超, 李国亮, 等. 港珠澳大桥青州航道桥设计[J]. 公路, 2014, 59(1):44-51. [4] 周继, 王新国, 严定国, 等.武汉市杨泗港快速通道跨线斜拉桥总体设计[J]. 桥梁建设, 2018, 48(6):87-92. [5] 刘士林, 王似舜. 斜拉桥设计[M]. 北京:人民交通出版社, 2006:47-50. [6] Nie J G.Application of steel-concrete composite structure in ocean engineering[J]. Steel Contruction (Chinese & English), 2020, 35(1):20-33. [7] 陈东生, 曲建军, 田新宇, 等.中国高速铁路工务维修管理体系探讨[J]. 铁道建筑, 2012(8):104-109. [8] 陈何峰, 励晓峰, 陶海, 等.宜兴市大溪河桥总体结构设计及计算[J]. 公路工程, 2010, 35(6):63-65, 81. [9] 孙秀贵, 王甜, 曾满良, 等.不同桥面形式的钢箱加劲梁受力性能比较研究[J]. 钢结构, 2018, 33(8):71-74, 89. [10] 杨仕力, 施洲.我国大跨径钢箱梁桥正交异性板疲劳损伤研究现状[J]. 桥梁建设, 2017, 47(4):60-65. [11] 孔祥福, 周绪红, 狄谨, 等.钢箱梁斜拉桥正交异性桥面板的受力性能[J]. 长安大学学报(自然科学版), 2007(3):52-56. [12] 中华人民共和国交通部.公路斜拉桥设计细则:JTG/T D65-01—2007[S]. 北京:人民交通出版社, 2007. [13] 吴伟胜, 王仁贵, 王梓夫.杭州湾跨海大桥航道桥钢箱梁设计[J]. 桥梁建设, 2006(3):24-26, 54. [14] 苟超, 郑凯锋, 栗怀广, 等.大跨斜拉桥钢箱梁正交异性桥面详细应力计算和桥面优化研究[J]. 钢结构, 2016, 31(12):82-87. [15] 张燕飞, 徐恭义, 胡辉跃.大跨宽幅重载斜拉桥设计关键技术[J]. 桥梁建设, 2020, 50(增刊1):1-7. [16] 王若林, 张慧敏.截面构造对钢箱梁剪力滞效应及其稳定性的影响[J]. 钢结构, 2017, 32(5):31-34, 84.
点击查看大图
计量
- 文章访问数: 522
- HTML全文浏览量: 134
- PDF下载量: 30
- 被引次数: 0