Steel Structure Selection and Design of Zhuhai New Air Show Hall
-
摘要: 作为珠海航展的主展示馆,航展馆屋盖造型新颖,柱位规整,且屋盖结构外露可见,优选建筑美观、受力合理的结构形式——空间四角锥网架+入口巨型桁架组合体系;根据机库门的不同开启模式设计4种不同工况用于风洞试验及后期设计,确保复杂风环境下的结构安全。根据结构特点,分别对屋盖结构形式、分缝做法、网架高度、球节点做法进行技术和经济比较。
根据建筑功能,首次在机库门上方设置三层立体桁架体系,上面两层与网架连接,下弦层作为贵宾厅的建筑使用层,利用机库门两侧的竖向交通空间设置立体桁架柱,与机库门上方的桁架梁构成整体结构刚度。从受力考虑,屋盖设置两道结构缝,分析屋盖传力路径,入口桁架承担了屋盖总荷载的85%。由于结构分缝的关系,网架受力应尽可能往机库门方向传递。采用人工干涉力流理念,对靠近机库门附近的网架横向弦杆进行局部抽空,利用刚度效应使得屋盖力流优先传至巨型桁架结构,满足力流控制需要。在满足舒适度需求下,对上人贵宾厅在不同行走路径下进行了舒适度分析。在满足不停航施工的严苛现场条件下,采用了"超大型构件液压同步提升技术"对整体结构分两次提升的方案。在满足安全、经济、美观的前提下,选择了合理的结构方案,并进行了连接节点设计。本工程用钢量适中,同时圆满完成了工期和成本方面的预期目标,取得了显著的社会和经济效益。Abstract: As the main exhibition hall of Zhuhai Air Show, the roof of the exhibition hall is of novel shape, regular column position and exposed roof structure. The structure form of beautiful and reasonable stress was selected:the space quadrangle cone truss and entrance mega truss combination system; according to the different opening modes of hangar door, four different working conditions were designed for wind tunnel test and later design to ensure the structural safety in complex wind environment. According to the structural characteristics, the technology and economy condition of the roof structure form, the split joint method, the height of the grid and the practice of ball joint were compared.
According to the building function, three-layer three-dimensional truss system was set above the hangar door for the first time. The upper two floors were connected with the network frame and the lower chord layer was used as the building floor of VIP Hall. The vertical traffic space on both sides of the hangar door was used to set up the three-dimensional truss column, which formed the overall structural rigidity with the truss beam above the hangar door. The aircraft did not need to be overhauled. Two structural joints were set for roof considering the stress. The load path of roof was analyzed, and the entrance truss born 85% of the total roof load. Due to the relationship between structural split, the stress of the grid frame should be transmitted to the direction of the hangar door as far as possible. The artificial interference force flow concept was adopted to make local evacuation for the transverse chord of the grid near the hangar door. The stiffness effect was used to make the force flow of roof transmit priority to the mega truss structure, so as to meet the needs of force flow control. In order to meet the comfort requirements, the comfort analysis of VIP Hall under different walking paths was carried out. In order to meet the strict site conditions of the project without stopping the navigation, it was determined that the "super large component hydraulic synchronous lifting technology" was adopted to upgrade the whole structure twice. On the premise of safety, economy and aesthetics, the reasonable structure scheme and connection nodes were designed. The steel quantity of the project was moderate. The expected target of construction period and cost has been successfully completed, and remarkable social and economic benefits have been achieved. -
[1] 中华人民共和国住房和城乡建设部. 建筑工程抗震设防分类标准:GB 50223—2008[S]. 北京:中国建筑工业出版社, 2008. [2] 广东省住房与城乡建设厅.建筑结构荷载规范:DBJ 15-101—2014[S]. 北京:中国建筑工业出版社, 2014. [3] 中华人民共和国住房和城乡建设部. 空间网格结构技术规程:JGJ 7—2010[S]. 北京:中国建筑工业出版社, 2010. [4] 中华人民共和国住房和城乡建设部.钢结构设计标准:GB 50017—2017[S]. 北京:中国建筑工业出版社, 2018. [5] 中华人民共和国住房和城乡建设部. 建筑楼盖振动舒适度技术标准:JGJ/T 441—2019[S]. 北京:中国建筑工业出版社, 2019.
点击查看大图
计量
- 文章访问数: 235
- HTML全文浏览量: 24
- PDF下载量: 52
- 被引次数: 0